Aeropac Launch Equipment 08
Trailer Launch Pads Launch Control PA System FM Transmitter Instruction Manual Launch rods
1. Trailer
Repair Running lights Task start
Replace missing lights
Solar breakaway charger Task start
Add 12 V line to Escalade plug.
Add solar panel to trailer roof.
Connect 12 V line to breakaway battery and inside trailer for launch battery charging.
Body corrosion Task start
Add cone reflectors Task start
2. Launch Pads
Blast Shields
Fab full-length rail bars.
Provide two clamp screws per shield
No-Tool Hardware
Inventory and replace any missing hardware
3. Launch Control
500' Pads Task start
Reconfigure control & battery dist cables.
Replace launch button.
1-10 Pads Task start
Remove battery junction boxes
11-20 Pads Task start
Remove battery junction boxes
21-30 Pads Task start
Remove battery junction boxes
Main Controller Task start
Test op, repair A/R
Replace siren button
4. PA System
Power save Task start
Power save mode inop. Modify circuit to respond to input.
5. FM Transmitter
Power Increase Task start
Deploy 40 watt amp. Use 15 watt as preamp
6. Instruction Manual
Master Manual
Online master to collect all info
Organized collection of task sheets
Add waiver info from Tony A
Task Sheets
HP & 1-10 sheets done
Change to landscape & trim to 7.5 X 10 for fit in vinyl
Mike on parking area & LCO area
7. Launch rods
Rail cleaning tank Task start
PVC or ABS tubing to fir largest rail.
Mix 1% NaOh to soak rails for cleaning.
Neutralize with HCl